  Prop S Budget Budget Actual Spent Remaining Budget Balance (unspent)
  Curriculum (Moss & Kopplin Fields, FACS, Knight Aud, Selma field) $21,579,400 $22,481,835 -$902,435
  Electric $416,500 $21,509 $394,991
  Exterior Lighting $1,190,000 $103,894 $1,086,106
  Mechanical $4,938,500 $5,390,830 -$452,330
  Outdoor Accessibility $476,000 $249,091 $226,909
  Roofs, Gutters, & Eaves $2,380,000 $2,506,259 -$126,259
  Exterior Doors and Windows $5,950,000 $1,277,021 $4,672,979
  Interior Finishes $3,620,500 $145,309 $3,475,191
  Masonry $2,094,970 $1,382,321 $712,649
  Pavement and Retaining Walls $2,380,000 $1,143,892 $1,236,108
  Safety and Security (includes interior doors) $4,893,530 $1,206,419 $3,687,111
  Premium & Interest (additional contingency) $480,600   $480,600
  Total $50,400,000 $35,908,380 $14,491,620

                                                                                   Updated 11.12.25